Site Preparation & Foundation Planning — Before your frame arrives, your site needs preparation and foundations ready to receive it. Here’s what’s involved in getting your site from raw land to frame-ready condition.

Site Assessment First
Before any physical work, understand your site. Key assessments include: surveyor’s site plan (boundaries, levels, existing features), geotechnical report (soil classification, bearing capacity), and any specific requirements (bushfire, flooding, heritage). These inform foundation design and site works scope.
Clearing and Access
Remove vegetation as required for the building footprint plus work areas. Check council requirements—some trees may be protected. Establish site access for delivery vehicles and construction traffic. Temporary access tracks may be needed on rural sites. Consider where you’ll store materials and park vehicles.
Erosion and Sediment Control
Most councils require erosion and sediment control measures during construction. Silt fences, hay bales, or sediment basins prevent soil washing off site. These are typically installed early and maintained throughout construction. Check your approval conditions for specific requirements.
Site Levelling
Depending on your foundation type and site topography, levelling may be required. Slab foundations typically need cut-and-fill to create a level pad. Elevated floors can accommodate slope with varied stump or pier heights. Excessive cut or fill has engineering implications—work with your site plan and geotech report.
Foundation Options
Concrete slab: Most common for level sites. Involves excavation, formwork, reinforcement, and concrete pour. Allows internal thermal mass. Requires precise set-out for frame alignment.
Stumps/piers: Concrete piers or adjustable steel stumps elevate the floor. Suits sloping sites and reactive soils. Allows underfloor access and ventilation. Our subfloor systems sit on stumps or piers—bearer and joist steel framing creates your floor platform.
Screw piles: Helical steel piles screw into ground without excavation. Fast installation, minimal site disturbance, good for difficult access. Suit our subfloor systems well. Higher per-pile cost but often lower total cost through speed.
Services Rough-In
Underground services (sewer, water, electrical, gas, communications) typically install before or during foundation work. Penetrations through slabs need precise positioning. Elevated floors offer more flexibility for service routing. Coordinate with trades early—moving services later is disruptive and costly.
Foundation Completion and Curing
Concrete foundations need curing time before loading. Typically 7-14 days minimum before frame erection commences. Plan this into your schedule—don’t assume same-day or next-day readiness. Confirm with your certifier when the structure can commence.
Ready for Frame
A frame-ready site has: completed foundations to engineering specifications, accurate set-out matching frame dimensions, approved inspections where required, and clear access for frame delivery and crane/equipment if needed. Coordinate delivery timing to avoid frames sitting exposed to weather.
Who designs my foundations?
Foundation engineering is typically separate from frame engineering. Your frame engineer may offer footing design, or you engage a separate engineer. Ensure foundation and frame engineering coordinate—they must work together.
What if my site is steeply sloped?
Elevated floors handle slope economically up to moderate grades. Steep sites may require retaining walls, cut platforms, or specialised foundation systems. Engineering costs increase with complexity. Site assessment reveals what’s involved.
Can I do site preparation myself?
Some work suits DIY—clearing, basic earthworks with hired equipment. Other work requires licensed operators or engineers. Assess your capabilities honestly; foundation problems are expensive to fix.
How accurate does foundation set-out need to be?
Very accurate—typically ±10mm. Pre-engineered frames expect foundations where specified. Significant errors require adjustment or cause fit problems. Engage a surveyor for set-out; it’s not expensive compared to correcting mistakes.